PROJECT NO. | PROJECT NAME | STATUS |
---|---|---|
17-002 | Final Project Proposal - Gymnasium Renovation | In DSA Review |
17-009 | Fox Field Improvements | COMPLETE |
17-030 | Swing Space Phase 1 | COMPLETE |
17-031 | Sage Hall | COMPLETE |
17-037 | Student Services Building (Demo LS1-LS2-OF3/Rel. T100) | Construction |
17-038 | Ave. J-12 Main Entry | Construction |
17-039 | Discovery Lab (Career Technology Education Building) (Rel. T503-T504) | COMPLETE |
17-040 | AVC Pavilion Project (Campus Security Building/Demo T800) (Tennis Courts/ | Construction (Security ONLY) |
Adap. PE Pool/Demo Tennis Courts/AVC Pavilion/Sand VB Courts CANCELED) | ||
17-041 | Marauder Complex | Construction |
17-042 | Project General Conditions & Logistics | On-Going |
17-043 | AT&T Baseball Stadium Cell Tower & Lighting | COMPLETE |
18-021 | Cedar Hall (Instructional Building 2-Demo SSV) | BIDDING |
18-003 | The Commons (Demo TE1-TE2-SS-ME-OF2) | Design |
18-010 | Waste & Recycling Center Renovation (17-005 rev.) | COMPLETE |
18-011 | Swing Space Phase 2 (LC, FA4 and/or Mod Bldgs) | Construction |
18-012 | Palmdale Center Technology Facility | COMPLETE |
18-017 | Campus Signage Replacement | COMPLETE |
20-003 | CSUB & University Center (Demo CSUB Bldgs) | CANCELED |
20-005 | BE Building, Classroom Modernization | Construction |
20-006 | Bookstore Remodel | Cancelled |
20-007 | Flooring Replacement, APL Building | COMPLETE |
20-008 | B2 Replica Repairs | ON HOLD |
20-009 | Fine Arts HVAC Replacement | BIDDING |
20-010 | Campus Flooring Replacement Phase 2 | COMPLETE |
20-011 | OBS & Risk Management Office Modernizations | COMPLETE |
20-012 | Fox Field Hangar Improvements | COMPLETE |
20-013 | PENDING PROJECT | |
20-014 | Palmdale Property Survey and Maintenance | COMPLETE |
20-015 | Tmobile Cell Tower Maintenance Upgrades | COMPLETE |
20-016 | PENDING PROJECT | |
20-017 | PENDING PROJECT | |
21-001 | Renaming Campus Buildings +B181:B201 | COMPLETE |
21-002 | Parking Lots - Asphalt repair/Replacement | In Review |
21-003 | Campus Electronic Lock Upgrades | In Progress |
21-004 | Campus Perimeter Security Gates | ON HOLD |
21-005 | Campus Elevator (3) Modernization | In Progress |
21-006 | Campus Fire Alarm Upgrade - EST Campus Standard | ON HOLD |
21-007 | Fine Arts Buildings Code Compliance & Modernization | ON HOLD |
21-008 | ADA Campus Wide Improvements | ON HOLD |
21-009 | BE Building Flooring Replacement | ON HOLD |
21-010 | Lecture Hall Building Code Compliance & Modernization | ON HOLD |
21-011 | CDC Building Upgrades & Roof Replacement | ON HOLD |
21-012 | Boiler Replacements (TE7 & FA) | In Progress |
21-013 | Library Roof Repairs | ON HOLD |
22-001 | Instructional Building 3 (Demo FA Bldgs.) | CANCELED |